Electric Cooperatives in 2026: System Loss, Financial Troubles and the Growing Burden on Consumers
- November 25, 2026
Table of Contents
Electric cooperatives (ECs) are key to the Philippines’ power distribution, particularly in rural areas. These private, non-profit, member-owned entities work with the National Electrification Administration (NEA), with 121 cooperatives supporting the government’s goal of total electrification by 2028.
Established largely during the 1970s and 1980s, ECs have access to government funding and subsidies to help build their networks and extend their reach across the countryside. However, the conditions that shaped their creation no longer reflect the demands of today’s economy.
Expanding cities and growing industries have driven electricity demand higher, straining distribution networks built for a different era. ECs must keep up by upgrading aging infrastructure, improving service reliability and expanding their reach, all of which require substantial capital. However, their non-stock, non-profit structure can limit access to the financing needed for these investments.
These structural challenges have become harder to ignore in 2026. Persistent system losses, financial difficulties, operational shortcomings, and complaints over electricity service have brought the sector’s vulnerabilities back into focus. For consumers, these problems can translate into higher electricity costs and unreliable power.
(Also read: Philippines, Indonesia, Vietnam Join Forces To Accelerate Solar Shift In Off-Grid Islands)
8 Major Issues Plaguing ECs in 2026
Several developments in 2026 have brought the performance and long-standing challenges of the country’s ECs back into the spotlight.
1. High electricity prices
Many consumers served by ECs are facing steep electricity rates. For instance, the Northern Samar Electric Cooperative (NORSAMELCO) recorded a residential rate of ₱16.907 per kilowatt-hour (kWh) in January 2026, reportedly the highest in the country that month.
The rate prompted Northern Samar 2nd District Rep. Edwin Ongchuan to seek a review of the cooperative’s billing practices and determine whether its charges were justified.
In June 2026, the Oriental Mindoro Electric Cooperative (ORMECO) posted a residential rate of ₱18.29/kWh, the highest among ECs connected to the main grid, according to consumer advocacy group Partners for Affordable and Reliable Energy (PARE). The group attributed the increase partly to the cooperative’s reliance on more expensive generation sources, with purchases from emergency power providers rising by 56.09%.
PARE has likewise warned that power supply agreements could lock consumers into higher electricity costs if ECs fail to secure the most affordable and reliable suppliers. It has called for these contracts to be made public, allowing member-consumers to scrutinize the decisions behind their electricity bills.
The Senate has also weighed in on the issue, with Sen. Sherwin Gatchalian calling for lower electricity costs. “If we want to revitalize our economy and give real financial relief to Filipino families and small businesses, we need to bring down the cost of electricity,” he said.
2. Unreliable power supply
Recurring blackouts have exposed weaknesses in several ECs’ distribution networks, with consumers and local economies bearing the consequences.
In May 2026, thousands of Bukidnon residents endured nearly 27 hours without electricity after a scheduled substation upgrade by the First Bukidnon Electric Cooperative (FIBECO) ran into technical problems. Repeated delays in restoring power, including an explosion during energization attempts, sparked public criticism. The disruption also affected Valencia City, Bukidnon’s commercial center, prompting local officials to seek intervention from the Department of Energy (DOE) over complaints of frequent and prolonged outages.
Siargao has faced similar problems, with power interruptions repeatedly disrupting daily life and economic activity. A December 2024 submarine cable fault cut the island and neighboring Bucas Grande off from the mainland grid, triggering a blackout that lasted two weeks and prompted a declaration of a state of calamity. The Center for Energy Research and Policy (CERP) estimated the economic damage at ₱1.09 billion, as hotels, resorts and restaurants suffered cancellations, lost income and temporary closures.
Another outage in December 2025, followed by a January 2026 interruption, renewed calls for reforms in the Siargao Electric Cooperative’s (SIARELCO) power network.
Beyond businesses, unreliable electricity has affected schools, forcing class suspensions and disrupting students’ learning. Advocacy groups have urged the government to treat energy security as an economic priority, particularly in tourism-dependent areas. They have also called for more diverse power sources and stronger infrastructure to prevent recurring outages.
3. Excessive system losses
System losses remain a major problem for ECs, with some recording rates far above the limits set by the Energy Regulatory Commission (ERC). In 2025, the combined operations of Albay Electric Cooperative (ALECO) and Albay Power and Energy Corp. (APEC) posted the highest loss rate at 21.5%, followed by Zamboanga City Electric Cooperative (ZAMCELCO) at 18.1%.
These inefficiencies carry substantial costs: ZAMCELCO alone recorded ₱543 million in system-loss expenses, while consumers nationwide are estimated to shoulder ₱6.82 billion annually from electricity theft, meter tampering, and illegal connections.
The figures have intensified calls to stop passing system-loss costs on to consumers. President Ferdinand Marcos Jr. has urged Congress to end the practice, while the NEA supports removing nontechnical losses from electricity bills. However, the agency warns that 89 ECs could suffer financial losses if the charge is completely scrapped without alternative support.
The debate highlights a deeper problem: consumers should not indefinitely pay for electricity lost through theft, poor maintenance or inefficient operations, but forcing cooperatives to absorb all losses could leave them unable to pay power suppliers or maintain their networks.
Government agencies are proposing investments in smart meters, distribution-line upgrades and anti-pilferage measures. NEA has also sought additional funding for system-loss reduction, including a ₱7-billion loan proposal. This would be in addition to the executive budget’s allocations of ₱850 million for EC loans and ₱5.64 billion for rural electrification.
Ultimately, reform requires stronger accountability. As energy experts have argued, utilities should not be rewarded with continued cost recovery when excessive losses stem from poor management or governance failures.
4. Financial strain & mounting debt
Aside from high system losses, ALECO also faced power supply constraints that led to rotating brownouts in parts of the province. Its financial position remains strained, with more than ₱656 million in Wholesale Electricity Spot Market (WESM) arrears and nearly ₱9.9 billion in total liabilities as of June 2025. The NEA has classified the EC as “ailing” for eight consecutive years.
The South Cotabato Electric Cooperative (SOCOTECO II) is in the same boat, reporting a ₱521.8-million net loss in 2025 and accumulated losses of ₱2.1 billion. Its aging distribution network requires substantial rehabilitation, estimated to cost around ₱10 billion. Negative cash flow and monthly losses have forced the EC to rely on government and commercial loans.
Meanwhile, the Lanao del Sur Electric Cooperative (LASURECO) has faced a longer-running debt problem. Its unpaid obligations to the Power Sector Assets and Liabilities Management Corp. (PSALM) reached approximately ₱11.98 billion in 2021 and exceeded ₱16 billion the following year, prompting the government to order a power disconnection. Congress later approved a measure seeking to condone accumulated interest, penalties, and universal charges while allowing the remaining debt to be restructured.
Unlike LASURECO, whose debts reflect financial distress, the Iloilo Electric Cooperatives (ILECO) I, II, and III maintained that their finances remain stable despite outstanding NEA loans totaling ₱100.6 million. They said the borrowings fund capital projects and improvements needed to meet growing electricity demand. NEA also confirmed that the loans support substation operations and distribution system upgrades.
5. Aging infrastructure
In 2024, the Negros Occidental Electric Cooperative (NONECO) came under criticism after a transformer malfunction at its 15-MVA Victorias substation disrupted electricity supply in E.B. Magalona, Manapla, and Victorias City. The incident affected an estimated 300,000 households. Local officials questioned the cooperative’s response time and communication with affected communities, particularly over when electricity would be restored.
The incident prompted discussions about possible partnerships with private DUs to address infrastructure and operational problems. In 2025, the Alliance of Concerned Consumers in Electricity and Social Services (ACCESS) expressed support for proposed partnerships involving Negros Power.
In Mindanao, Samal Island’s ambitions as a tourism and investment hub were hampered for years by an unreliable power supply under NORDECO. Recurring outages disrupted businesses and households, while local estimates put annual economic losses at ₱120 million to ₱150 million since the 2010s. Unstable electricity also discouraged potential investors, while a proposed ₱1.1-billion submarine cable connection to Pantukan remained unfinished under the cooperative.
In 2026, Davao Light took over Samal’s power distribution and inaugurated a 1.25-kilometer submarine cable linking the island to Davao. The 69-kilovolt (kV) interconnection can deliver up to 50 MW, strengthening the island’s power supply.
A study by the Institute for Contemporary Economics (ICE) found that seven electric cooperatives in Panay and Guimaras spent only ₱2.38 billion of their ₱10.52-billion capital expenditure budget for 2022–2024, with much of the funds going to routine maintenance rather than infrastructure upgrades.
The shortfall limited improvements to substations, distribution lines, and protection systems, potentially increasing outage risks and undermining service reliability and economic activity, particularly in island communities.
(Also read: H&WB Pushes Ahead With 700-MW Coal Plant Despite Moratorium)
6. Public funding and accountability
Proposals to restructure the debts of struggling ECs have renewed questions about the sector’s financial management, oversight and dependence on government support. The debate intensified in February 2026, when Representative Lawrence Dagooc called for a “universal debt restructuring program” that would transfer interest payments, penalties and surcharges on EC loans to government agencies, including NEA and National Power Corporation (Napocor).
PhilStar columnist Bienvenido Oplas criticized the proposal, arguing that it would shift the cost of persistent inefficiencies to taxpayers rather than address the sector’s underlying problems.
“His (Dagooc’s) statements and proposals are additional proof that most, if not all, ECs are inefficient and wasteful, created by politics, monitored and protected by politics via NEA, and kept afloat by tax money via NEA loans to them taken from taxpayers’ money,” Oplas wrote.
Government assistance, however, also finances projects intended to improve electricity service. In 2025, NEA extended about ₱2.8 billion in loans to 45 ECs nationwide, including ₱1.7 billion for capital expenditures by 34 cooperatives. Its Enhanced Lending Program also provides financing for system upgrades, renewable energy projects, disaster recovery, and modular generator sets.
Still, public funding has not eliminated accountability issues. In a performance audit released in April 2026, the Commission on Audit (COA) reported that ₱953 million in rural electrification subsidies remained unliquidated, with outstanding documentation and inspection requirements delaying their settlement. COA also faulted NEA for releasing new subsidies to cooperatives with outstanding balances.
Separately, another COA report found that ₱1.21 billion in disaster-related subsidies released to 87 ECs remained unliquidated as of December 2024, citing delays in project implementation, inspection, and fund accounting.
7. Support for private sector entry
Calls for private sector participation in electricity distribution have gained traction in several provinces.
In Batangas, nearly 2,000 residents and business owners in Laiya petitioned in March 2026 for Meralco to take over electricity services, citing frequent interruptions, damaged appliances, and poor customer service. The petitioners said unreliable power had disrupted households, businesses, and tourism activities, affecting students, workers, and small business owners. They also questioned the Batangas Electric Cooperative (BATELEC) II’s ability to meet rising demand as the area’s population and tourism industry expanded.
The appeal followed earlier calls for changes in the province’s power distribution system. In November 2025, the Batangas Forum for Good Governance and Development Association Inc., composed of business leaders, professionals, and residents, endorsed a proposed joint venture between Meralco and BATELEC II. The group cited recurring power disruptions and their effects on business operations and provincial development.
A similar proposal has emerged in Iloilo, where consumer group Bantay ng Bayan-101 urged the Iloilo 1 Electric Cooperative (ILECO 1) to consider partnering with MORE Power if the latter’s proposed franchise expansion proceeds. The group represents consumers in seven municipalities in the province’s first district and argued that cooperation would be more practical than competing for customers.
It also pointed to the 2024 MORE Power-Central Negros Electric Cooperative (CENECO) joint venture as a possible model for modernizing distribution infrastructure and expanding service coverage. The proposal comes amid continuing discussions over electric cooperatives’ franchise rights and the role of private utilities in improving electricity services.
8. Awards and recognition versus actual service performance
Annual awards from NEA and the Philippine Rural Electric Cooperatives Association (PHILRECA) are intended to promote accountability and recognize strong performance among ECs. Yet high institutional ratings do not always reflect consumers’ experiences with electricity service.
However, the records of some award-winning cooperatives reveal a more complicated picture. The First Bukidnon Electric Cooperative (FIBECO), among the recipients of multiple distinctions at the 2025 NEA-EC Convergence, was recognized as a Most Improved Electric Cooperative and received awards for household energization, prompt payments, and financial discipline.
That same year, however, NEA filed criminal complaints against FIBECO officials over alleged fund irregularities involving a former general manager. The complaints included an unauthorized ₱11.55-million land acquisition that did not materialize and the alleged transfer of ₱6 million to a personal account. FIBECO has also faced consumer complaints over electricity rate increases that customers said were inadequately explained.
The Ilocos Norte Electric Cooperative (INEC) also received several distinctions at the 2025 NEA Lumens Awards, including its second consecutive Top Performing Electric Cooperative Award for its 2024 performance.
Despite these accolades, the cooperative faced scrutiny over alleged financial irregularities. In 2025, NEA filed criminal complaints against current and former officials over the alleged misuse of approximately ₱118 million from INEC’s Employees’ Retirement Fund. The case involved allegations of syndicated estafa and included several executives and department heads.
Putting Consumers Ahead of the Cooperative Model
The challenges facing ECs in 2026 point to a need for reforms that go beyond government subsidies and performance awards. While public support remains important to rural electrification, it cannot become a permanent substitute for efficient management and reliable electricity delivery. Consumers should not have to shoulder the cost of persistent losses and inadequate infrastructure.
The Supreme Court has made clear that electricity distribution franchises must serve the public interest, not protect providers from competition. As the Court stated, “A franchise, as a privilege granted by the state, is not the exclusive private property of the franchisee.” This establishes that existing service territories can be changed when Congress determines that doing so serves the common good.
Greater private-sector participation could help address the capital and technical limitations that constrain some ECs. Partnerships with established utilities may bring investment, modern distribution technologies, better-trained personnel, and stronger operational management. Other proposals, including changes to the cooperative ownership and governance structure, also deserve serious consideration, provided consumer protections remain central.
The objective should not be privatization for its own sake, but a distribution system capable of meeting rising electricity demand without placing an unsustainable burden on households and businesses. Any transition must preserve access to affordable power, particularly in underserved communities, while holding providers accountable for their performance.
Electricity is an essential public service, not a privilege tied to the structure or ownership of a distribution utility. Whether operated by a cooperative, a private company, or a partnership between the two, every provider must meet the same standards of affordability, reliability, transparency, and efficiency.
Ultimately, the success of rural electrification should not be measured by the number of cooperatives maintained, loans released, or awards received. It should be measured by whether consumers receive dependable electricity at reasonable rates. When a provider repeatedly fails to deliver, reform—including competition or a change in operator—must remain an option.
Sources:
https://tribune.net.ph/2026/08/22/co-ops-must-open-up-for-private-capital
https://tribune.net.ph/2026/08/13/albay-co-ops-top-system-loss-list
https://www.rappler.com/business/national-electrification-administration-2027-budget-system-loss
https://newsinfo.inquirer.net/2231696/extended-blackout-sparks-consumer-outrage-in-bukidnon
https://powerphilippines.com/ilaw-calls-for-urgent-power-reforms-after-another-siargao-blackout
https://tribune.net.ph/amp/story/2026/03/18/solon-seeks-review-of-power-bills-charges
https://tribune.net.ph/amp/story/2026/01/28/davao-light-granted-provisional-authority-for-expansion
https://www.philstar.com/nation/2024/10/18/2393365/power-outages-hit-3-negros-areas
https://sc.judiciary.gov.ph/sc-exclusive-franchises-are-prohibited-by-the-constitution
https://www.sunstar.com.ph/davao/mayor-samal-loses-p120-p150m-yearly-due-to-unresolved-power-woes
https://www.sunstar.com.ph/davao/davao-samal-submarine-cable-launched-to-stabilize-power
https://tribune.net.ph/2026/03/24/batangas-residents-seek-meralco-entry-amid-power-woes
https://www.dailyguardian.com.ph/blog/group-pushes-ileco-1-more-power-joint-venture
https://docs.congress.hrep.online/legisdocs/basic_20/HB04017.pdf
https://www.dailyguardian.com.ph/blog/socoteco-ii-faces-php-2-1-billion-loss-infrastructure-backlog
https://www.philstar.com/business/2022/06/09/2186990/psalm-cuts-electric-supply-2-power-coops
https://bworldonline.com/the-nation/2025/05/27/675337/nea-files-case-vs-2-power-co-ops